Task relations

relations tasks

Easy8 provides 8 types of task relations

related to - Just adds a link to the other task.
duplicates - Links tasks so that closing one, will close the other (e.g. closing A will close B). For

example, if task B duplicates A:
- closing B will leave A open
- closing A will automatically close B

duplicated by - Reciprocal of duplicates.
For example, if task A is duplicated by task B: - closing B will leave A open
- closing A will automatically close B

blocks - Links tasks so that closing one can be blocked by an task which is still open. If task B blocks A, A can't be closed unless B is.

blocked by - Reciprocal of blocks.
precedes - Links tasks to define an "order", where A needs to be completed x days before B can be

started on. If B follows A, you can't give B a starting date equal or less than the ending date of A. • follows - Reciprocal of precedes.

If task B follows A (ex A ends the 21/04 and B begin the 22/04)and you add +2 day at the

ending date of A, the starting and ending dates of B will be +2 too.
copied from - Links tasks to identify whether it was copied, and from which task it was copied from. • copied to - Reciprocal of copied from.

To add a new task relation, Easy Project provides 2 variant:
1. On particular tasks in More menu choose the option Add related task