Introduction
This guide shows you how to manually run the recalculation for Earned Value Management (EVM) in Easy8. Manual recalculation updates the project's Actual Cost and Earned Value lines so you can compare them to the Planned Value line based on the most recent data.
Target Audience
- Administrator
Prerequisites
- EVM module must be configured on the project
- Access to Administration >> Overview of scheduled tasks
How to Manually Run Recalculation
Step 1: Access Scheduled Tasks
- Go to Administration in the global menu
- Select Overview of scheduled tasks
Step 2: Run Earned Value Updater
- Find the task named Earned value updater
- Click the option to run it manually
- This recalculates the Actual Cost and Earned Value lines for the project
- These lines will be updated to reflect all changes made, not just for today
Step 3: Understand the Reload Constantly Option
- If Reload constantly is enabled (checked), the recalculation applies to all past project data
- If it is disabled (unchecked), only changes from the current day are included
Conclusion
You have now run a manual recalculation of Earned Value data in Easy8. This ensures your project metrics like Actual Cost and Earned Value are fully up to date and accurately compared against the Planned Value curve.